CASE PROCESSING PROCEDURES; DEFERRAL TO ARBITRATION – Pre-Arbitration

Single Topic for Decision 2155M


View all topics for Decision 2155M

Full Decision Text (click on the link to view): Full Text

1102.00000 – CASE PROCESSING PROCEDURES; DEFERRAL TO ARBITRATION
1102.01000 – Pre-Arbitration

* * * OVERRULED IN PART ON OTHER GROUNDS by Santa Clara Valley Water District (2013) PERB Decision No. 2349- M. * * *

An arbitration clause in a grievance process does not continue in effect after the expiration of the contract except for disputes that: (1) involve facts and occurrences that arose before expiration; (2) involve post-expiration conduct that infringes on rights accrued or vested under the agreement; or (3) under normal principles of contract interpretation, survive the expiration of the agreement.