CASE PROCESSING PROCEDURES; DEFERRAL TO ARBITRATION – Post Arbitration; Repugnancy
Single Topic for Decision 2170M
View all topics for Decision 2170M
Full Decision Text (click on the link to view): Full Text
1102.00000 – CASE PROCESSING PROCEDURES; DEFERRAL TO ARBITRATION
1102.02000 – Post Arbitration; Repugnancy
1102.02000 – Post Arbitration; Repugnancy
The Board deferred to the binding decision of the personnel commission convened pursuant to the final step of the grievance procedure in the parties’ MOU. The commission proceedings were essentially a binding arbitration, the commission was presented with and considered all of the evidence relevant to the unfair practice charge, and its decision that the employer’s imposition of furloughs did not violate the MOU was not repugnant to the MMBA. Thus, the Board dismissed the charge pursuant to PERB Regulation 32620(b)(6).